Schedule of Construction

Completion of discrete module systems leads to earlier electricity generation as modules can be operating while others are completing their installation.

Reduced site construction time as a result of factory manufacturing and modularization reduces financial risk and lowers financing costs.

Schedule based on 51 months mobilization to mechanical completion; 28.5 months critical path - first safety concrete to mechanical completion.

Reduced construction time: 51 months from mobilization to mechanical completion; 28.5 months from first safety concrete to mechanical completion
NuScale Plant Construction Sequence